03 — Example project

Project BV-0001 · Sheet 1 of 1

Front Entry Deck Replacement.

Location
Melbourne, VIC
Type
Decking / Outdoor

The homeowner's brief

“I want to rebuild my front entrance deck and replace the old decking boards.”

BeforeExisting timber front entry deck
VisualisationProposed visualisation of new front entry deck
Visualisation shows the proposed result, not a completed project.

01 — Expected contractor range

$3,800–$4,500

04 — Expected timeframe

2.5–3 days

Materials
$1,550
Labour
$1,800
Other
$600

02 — Material breakdown

Merbau decking boardsapprox. 9 m²
Treated pine joists & bearersas required
Fixings, screws & oil finishallowance
Estimated total$1,550

03 — Labour breakdown

Remove & dispose old deckingCarpenter
Repair / replace subframeCarpenter
Lay boards, steps & finishCarpenter
Estimated total$1,800

05 — Factors that could change the final price

  • +Condition of the existing subframe once boards are lifted
  • +Final measurements on site
  • +Timber species and finish selected
  • +Site access and waste removal
  • +Changes to scope
  • +Individual contractor pricing